Every EV charge point has to be registered with the company that owns the network your house is connected to — Northern Powergrid across most of our patch. We handle that part, but here's what's actually going on.

Route 1 · Connect and notify

Fit it, then tell them

Most ordinary home installs go this way. The charger is fitted and the network operator is notified within 28 days. That applies where:

  • It's one charge point going in, not several, and not a charger plus a heat pump at the same time
  • The maximum demand of the house stays at or below 13.8 kVA per phase — roughly a 60A supply
  • The main cut-out fuse rating is known and the supply can carry the load
  • The supply isn't looped — shared with next door — and there's nothing wrong with the network's own gear
Route 2 · Apply first

Permission before we start

Some jobs have to be approved before a cable goes anywhere near the wall. We submit the application and wait for the answer where:

  • The load would take the property over 60A per phase
  • More than one unit is going in, or a charger alongside a heat pump
  • The service is looped, or the supply needs upgrading
  • It's a commercial, three-phase or CT-metered site — where the charger's output has to sit within 30% of the agreed import capacity

For loads between 60A and 100A the network operator normally comes back within 10 working days. Larger jobs run to their published connection timescales.

The one that catches people out

A looped supply — where your house and your neighbour's share one service cable from the street — has to be split by the network operator before a charger can go on, and that's their job, not ours. It's free, but it takes time and it's the single most common reason an EV install gets held up. We check for it before quoting, so you hear about it at the start rather than on fitting day. Where a supply is tight, a load-limiting device that throttles the charger when the house is drawing heavily can often keep the job inside the simpler route instead.

What we handle

  • Maximum demand assessment before we quote
  • Checking your cut-out rating and whether the supply is looped
  • The notification or application, submitted by us
  • Load limiting designed in where the supply is tight
  • Installation certificate and paperwork on completion
  • Home or workplace, single or three phase