Fit it, then tell them
Most ordinary home installs go this way. The charger is fitted and the network operator is notified within 28 days. That applies where:
- It's one charge point going in, not several, and not a charger plus a heat pump at the same time
- The maximum demand of the house stays at or below 13.8 kVA per phase — roughly a 60A supply
- The main cut-out fuse rating is known and the supply can carry the load
- The supply isn't looped — shared with next door — and there's nothing wrong with the network's own gear